LOPEZ, J., J.:
To fulfill its contractual obligations, FMCS entered into another agreement (FMCS-MJAS Services Agreement)[8] with MJAS Zenith Geomapping & Surveying Services (MJAS) to subcontract some of the tasks it undertook under the FMCS-Eastern Services Agreement. The relevant portion of the FMCS-MJAS Services Agreement states:
1) Site Survey, Landing site determination and routing design, 2) Archival Research for Desk Top [sic] Study, Submarine cable route design, 3) Project planning, 4) Final Desk Top Study Report, and 5) Vessel Arrangement and Mobilizations[.][7]
WHEREAS, in the Service[s] Agreement by and between Eastern Telecommunications Philippines, Globe Telecom, Inc.[,] InfiniVAN, Inc., and Fleet Marine Cable Solutions Inc. dated 7 December 2020, it is agreed that Eastern Telecommunications Philippines, Globe Telecom, Inc.[,] InfiniVAN, Inc. contracted FMCS to carry out the Services required by Eastern Telecommunications Philippines, Globe Telecom, Inc.[,] InfiniVAN, Inc. Further, FMCS is allowed to subcontract the scope of work in whole or in part to any third party or subcontractor.Under the FMCS-MJAS Services Agreement the responsibilities of MJAS include, among others, the following:
WHEREAS, in the Service[s] Agreement by and between Eastern Telecommunications Philippines, Globe Telecom, Inc.[,] InfiniVAN, Inc., and Fleet Marine Cable Solutions Inc. dated 7 December 2020, parties therein will build and construct a new high capacity domestic fiber-optic submarine network that will connect various islands in Luzon, Visayas and Mindanao at the highest quality possible but at the most cost-efficient means on an ownership basis.[9] (Emphasis in the original)
4.2.1 Under Phase 1 of the project, the Subcontractor is responsible for the preparation of the report/ output performed by the Third-Party Contractor secured by Contractor to perform the Site Survey, Landing site determination and routing design, Archival Research for Desk Top Study, Submarine cable route design, Project planning and Final Desk Top Study Report. Under Phase 2 of the project, the Subcontractor is responsible for Marine Cable Route Survey and Burial Assessment.[10]On June 5, 2021, FMCS entered into another agreement,[11] this time with Kokusai Cable Ship Co., Ltd. (KCS) (FMCS-KCS Services Agreement).[12] This covers the Marine Cable Route Survey and Burial Assessment.[13]
REFERENCE | BILLED (USD) | 12% VAT (USD) | TOTAL AMOUNT DUE (USD) | 2% EWT (USD) | TOTAL AMOUNT PAID (USD) |
SI No. 1188 | 616,391.17 | 73,966.94 | 690,358.11 | 12,327.82 | 678,030.29 |
SI No. 1261 | 205,463.72 | 24,655.65 | 230,119.37 | 4,109.27 | 226,010.10 |
| 821,854.89 | 98,622.59 | 920,477.48 | 16,437.10 | 904,040.38 |
WHEREFORE, the foregoing premises considered, the Tribunal rules as follows –In dismissing, the claims and counterclaims of the parties, the CIAC ruled that the FMCS-MJAS Services Agreement does not constitute a construction contract.[29] It emphasized that though MJAS undertook to carry out the off-shore and in-shore marine route surveys, and to provide vessel personnel and equipment,[30] it made no reference to any activity that would be considered a construction activity. Thus, it concluded that there is no construction dispute to speak of.[31]SO ORDERED.[28]
- Inasmuch as the contract between the claimant and MJAS (Annex B, Complaint) is not a construction contract or does not involve construction in the Philippines, the CIAC and this Tribunal have no jurisdiction or authority to resolve the dispute subject of this arbitration.
- The claims and counterclaims of the parties against each other are dismissed. Without Prejudice.
- The parties shall bear their respective shares of the costs.
The CIAC has no jurisdiction over the claim of FMCS arising from the FMCS-MJAS Services Agreement |
RULE 2.4. Policy Implementing Competence-Competence Principle. — The arbitral tribunal shall be accorded the first opportunity or competence to rule on the issue of whether or not it has the competence or jurisdiction to decide a dispute submitted to it for decision, including any objection with respect to the existence or validity of the arbitration agreement. When a court is asked to rule upon issue/s affecting the competence or jurisdiction of an arbitral tribunal in a dispute brought before it, either before or after the arbitral tribunal is constituted, the court must exercise judicial restraint and deter to the competence or jurisdiction of the arbitral tribunal by allowing the arbitral tribunal the first opportunity to rule upon such issues.In the present case, the CIAC already ruled that it does not have jurisdiction over the dispute as the FMCS-MJAS Services Agreement makes no reference to any activity that would be considered as a construction activity.[57] CIAC Arbitrator Salvador S. Panga, Jr. (Arbitrator Panga) dissented, insisting, among others, that while the contract involved only marine survey and does not actually pertain to laying of submarine cables, it is still critical and intimately related to the accomplishment of the main project to build a new high capacity domestic fiber-optic submarine cable network.[58]
Where the court is asked to make a determination of whether the arbitration agreement is null and void, inoperative or incapable of being performed, under this policy of judicial restraint, the court must make no more than a prima facie determination of that issue.
Unless the court, pursuant to such prima facie determination, concludes that the arbitration agreement is null and void, inoperative or incapable of being performed, the court must suspend the action before it and refer the parties to arbitration pursuant to the arbitration agreement.
The foregoing arbitration clause reflects the commitment of the parties to submit disputes arising from the contract. They agreed that any dispute, controversy, or claim arising out of or relating to the FMCS-MJAS Services Agreement shall be referred to and be resolved by arbitration under the Rules of Arbitration of the International Chamber of Commerce by one or more arbitrators appointed in accordance with the said Rules in the Philippines.[61] The arbitration clause is binding between FMCS and MJAS and they are expected to abide by it in good faith.Article 11 Applicable Law and Arbitration
11.1 This Agreement shall be construed and governed by the laws of the Republic of the Philippines without reference to any conflicts of law.
11.2 The Parties hereto shall use their best endeavors to settle all disputes arising out of or in connection with this Agreement or its supplement amicably.
11.3 If any dispute, controversy, or claim arising out of or relating to this Agreement cannot be settled by the Parties amicably, whether contractual or tortious, shall be referred to and finally resolved by arbitration under the Rules of Arbitration of the International Chamber of Commerce by one or more arbitrators appointed in accordance with the said Rules. The language of the arbitration shall be English, and the place of arbitration shall be in Republic of the Philippines. The arbitration award shall be final and binding upon both Parties. All costs and expenses related to the arbitration shall be borne by the non-prevailing Party.
11.4 In the course of arbitration, both Parties shall continue to perform their respective contractual obligations except those matters referred to arbitration.
11.4.1 Should it be necessary that an action be brought in court to enforce the terms of this Agreement of the duties and rights of the parties thereto, it is agreed that the venue for litigation should be the courts of the City of Makati to the exclusion of any other courts.[60] (Emphasis in the original)
Under the present Rules of Procedure, for a particular construction contract to fall within the jurisdiction of CIAC, it is merely required that the parties agree to submit the same to voluntary arbitration. Unlike in the original version of Section 1, as applied in the Tesco case, the law as it now stands does not provide that the parties should agree to submit disputes arising from their agreement specifically to the CIAC for the latter to acquire jurisdiction over the same. Rather, it is plain and clear that as long as the parties agree to submit to voluntary arbitration, regardless of what forum they may choose, their agreement will fall within the jurisdiction of the CIAC, such that, even if they specifically choose another forum, the parties will not be precluded from electing to submit their dispute before the CIAC because this right has been vested upon each party by law, i.e., E.O. No. 1008.[63] (Citation omitted)In its Complaint,[64] FMCS justified its resort to the CIAC by stating that the "case involves a construction dispute arising out of a construction project in the Philippines which falls within the original and exclusive jurisdiction of the CIAC, notwithstanding any reference to any other arbitral body."[65] This finds support in the CIAC Revised Rules, Rule 4, Section 4.1 which states:
SECTION 4.1. Submission to CIAC Jurisdiction. — An arbitration clause in a construction contract or a submission to arbitration of a construction dispute shall be deemed an agreement to submit an existing or future controversy to CIAC jurisdiction, notwithstanding the reference to a different arbitration institution or arbitral body in such contract or submission.In examining whether the present case is within the scope of the CIAC, this Court is guided by E.O. No. 1008, Section 4 which states:
SECTION 4. Jurisdiction. — The CIAC shall have original and exclusive jurisdiction over disputes arising from, or connected with, contracts entered into by parties involved in construction in the Philippines, whether the dispute arises before or after the completion of the contract, or after the abandonment or breach thereof. These disputes may involve government or private contracts. For the Board to acquire jurisdiction, the parties to a dispute must agree to submit the same to voluntary arbitration.The foregoing provision was reiterated in Rule 2, Section 2.1 of the CIAC Revised Rules, which states:
The jurisdiction of the CIAC may include but is not limited to violation of specifications for materials and workmanship; violation of the terms of agreement; interpretation and/or application of contractual time and delays; maintenance and defects; payment, default of employer or contractor and changes in contract cost.
Excluded from the coverage of this law are disputes arising from employer-employee relationships which shall continue to be covered by the Labor Code of the Philippines.
SECTION 2.1. Jurisdiction. — The CIAC shall have original and exclusive jurisdiction over disputes, which arose from, or is connected with contracts entered into by parties involved in construction in the Philippines whether the dispute arose before or after the completion of the contract, or after the abandonment or breach thereof. These disputes may involve government or private contracts.Based on the foregoing provisions, there are three essential requisites for the CIAC to acquire jurisdiction over a case: (1) a dispute arising from or connected with a construction contract; (2) such contract was entered into by parties involved in construction in the Philippines; and (3) the parties agreed to submit their dispute to arbitration.[66]
2.1.1 The jurisdiction of the CIAC may include but is not limited to violation of specifications for materials and workmanship; violation of the terms of agreement; interpretation and/or application of contractual provisions; amount of damages and penalties; commencement time and delays; maintenance and defects; payment default of employer or contractor and changes in contract cost. (Emphasis in the original)
Even the FMCS-MJAS Services Agreement, the subcontractor's agreement emanating from the FMCS-Eastern Services Agreement, does not involve any construction activity. To recall, the tasks MJAS committed to perform as subcontractor are as follows:
1) Site Survey, Landing site determination and routing design, 2) Archival Research for Desk Top Study, Submarine cable route design, 3) Project planning, 4) Final Desk Top Study Report, and 5) Vessel Arrangement and Mobilizations[.][77]
4.2.1 Under Phase 1 of the project, the Subcontractor is responsible for the preparation of the report/ output performed by the Third-Party Contractor secured by Contractor to perform the Site Survey, Landing site determination and routing design, Archival Research for Desk Top Study, Submarine cable route design, Project planning and Final Desk Top Study Report. Under Phase 2 of the project, the Subcontractor is responsible for Marine Cable Route Survey and Burial Assessment.[78]Given the foregoing definition of construction, it is clear that the cause of action of FMCS does not proceed from any construction contract or any controversy or dispute connected with it. To construe E.O No. 1008, Section 4, and CIAC Revised Rules, Rule 2, Section 2.1 as to include a suit for the collection of money and damages arising from a purported breach of a contract involving purely marine surveying activities and supply of vessel personnel and equipment would unduly and excessively expand the ambit of jurisdiction of the CIAC to include cases that are within the jurisdiction of other tribunals.
Under Phase Two, MJAS shall take on the marine cable route survey and burial assessment.[3]
1) Site Survey, Landing site determination, and routing design; 2) Archival Research for Desk Top Study, Submarine cable route design, 3) Project planning; and 4) Final Desk Top Study Report[.][2]
Republic Act No. 9285 or, the Alternative Dispute Resolution Act, provides that arbitration of construction disputes are covered by Executive Order No. 1008, or the Construction Industry Arbitration Law.[12]CHAPTER 6
Arbitration of Construction Disputes
SECTION 35. Coverage of the Law. — Construction disputes which fall within the original and exclusive jurisdiction of the Construction Industry Arbitration Commission (the "Commission") shall include those between or among parties to, or who are otherwise bound by, an arbitration agreement, directly or by reference whether such parties are project owner, contractor, subcontractor, fabricator, project manager, design professional, consultant, quantity surveyor, bondsman or issuer of an insurance policy in a construction project.
The Commission shall continue to exercise original and exclusive jurisdiction over construction disputes although the arbitration is "commercial" pursuant to Section 21 of this Act. (Emphasis supplied)
SECTION 4. Jurisdiction. — The CIAC shall have original and exclusive jurisdiction over disputes arising from, or connected with, contracts entered into by parties involved in construction in the Philippines, whether the dispute arises before or after the completion of the contract, or after the abandonment or breach thereof. These disputes may involve government or private contracts. For the Board to acquire jurisdiction, the parties to a dispute must agree to submit the same to voluntary arbitration.Thus, the Construction Industry Arbitration Commission has jurisdiction over disputes connected with contracts between parties involved in construction in the Philippines, so long as the parties have agreed to submit their disputes to arbitration.
The jurisdiction of the CIAC may include but is not limited to violation of specifications for materials and workmanship; violation of the terms of agreement; interpretation and/or application of contractual time and delays; maintenance and defects; payment, default of employer or contractor and changes in contract cost.
Excluded from the coverage of this law are disputes arising from employer-employee relationships which shall continue to be covered by the Labor Code of the Philippines. (Emphasis supplied)
Under the present Rules of Procedure, for a particular construction contract to fall within the jurisdiction of CIAC, it is merely required that the parties agree to submit the same to voluntary arbitration. Unlike in the original version of Section 1, as applied in the Tesco case, the law as it now stands does not provide that the parties should agree to submit disputes arising from their agreement specifically to the CIAC for the latter to acquire jurisdiction over the same. Rather, it is plain and clear that as long as the parties agree to submit to voluntary arbitration, regardless of what forum they may choose, their agreement will fall within the jurisdiction of the CIAC, such that, even if they specifically choose another forum, the parties will not be precluded from electing to submit their dispute before the CIAC because this right has been vested upon each party by law, i.e., E.O. No. 1008.[13] (Emphasis supplied, citation omitted)In Camp John Hay Development Corp. v. Charter Chemical and Coating Corp.,[14]
For the Construction Industry Arbitration Commission to acquire jurisdiction, the law merely requires that the parties agree to submit to voluntary arbitration any dispute arising from construction contracts.The parties in this case undeniably agreed to submit any dispute between them to voluntary arbitration. The subcontracting agreement between FMCS and MJAS provides:
In HUTAMA-RSEA Joint Operations, Inc. v. Citra Metro Manila Toll ways Corporation:Under Section 1, Article III of the CIAC Rules, an arbitration clause in a construction contract shall be deemed as an agreement to submit an existing or future controversy to CIAC jurisdiction, "notwithstanding the reference to a different arbitration institution or arbitral body in such contract[.]". . . .
[T]he arbitration clause in the construction contract ipso facto vested the CIAC with jurisdiction. This rule applies, regardless of whether the parties specifically choose another forum or make reference to another arbitral body. Since the jurisdiction of CIAC is conferred by law, it cannot be subjected to any condition; nor can it be waived or diminished by the stipulation, act or omission of the parties, as long as the parties agreed to submit their construction contract dispute to arbitration, or if there is an arbitration clause in the construction contract. The parties will not be precluded from electing to submit their dispute to CIAC, because this right has been vested in each party by law.It bears to emphasize that the mere existence of an arbitration clause in the construction contract is considered by law as an agreement by the parties to submit existing or future controversies between them to CIAC jurisdiction, without any qualification or condition precedent. To affirm a condition precedent in the construction contract, which would effectively suspend the jurisdiction of the CIAC until compliance therewith, would be in conflict with the recognized intention of the law and rules to automatically vest CIAC with jurisdiction over a dispute should the construction contract contain an arbitration clause[.]. . . .
Here, petitioner and respondent agreed to submit to arbitration any dispute arising from the construction contract, as clearly stipulated in their Contractor's Agreement. The arbitration clause should, thus, be given primacy in accordance with the State's policy to favor arbitration. It follows that if there is any doubt as to what provision should be given effect, this Court will rule in favor of the arbitration clause.[15] (Citations omitted)
Article 11 Applicable Law and ArbitrationWhile the parties named the Rules of Arbitration of the International Chamber of Commerce as the governing rule, they agreed to have their disputes be referred to and resolved by arbitration.
11.1 This Agreement shall be construed and governed by the laws of the Republic of the Philippines without reference to any conflicts of law.
11.2 The Parties hereto shall use their best endeavors to settle all disputes arising out of or in connection with this Agreement or its supplement amicably.
11.3 If any dispute, controversy, or claim arising out of or relating to this Agreement cannot be settled by the Parties amicably, whether contractual or tortious, shall be referred to and finally resolved by arbitration under the Rules of Arbitration of the International Chamber of Commerce by one or more arbitrators appointed in accordance with the said Rules. The language of the arbitration shall be English, and the place of arbitration shall be in Republic of the Philippines. The arbitration award shall be final and binding upon both Parties. All costs and expenses related to the arbitration shall be borne by the non-prevailing Party.
11.4 In the course of arbitration, both Parties shall continue to perform their respective contractual obligations except those matters referred to arbitration.
11.4.1 Should it be necessary that an action be brought in court to enforce the terms of this Agreement of the duties and rights of the parties thereto, it is agreed that the venue for litigation should be the courts of the City of Makati to the exclusion of any other courts.[16] (Emphasis supplied)
WHEREAS, in the Service[s] Agreement by and between Eastern Telecommunications Philippines, Globe Telecom, Inc.[,] InfiniVAN, Inc., and Fleet Marine Cable Solutions Inc. dated 7 December 2020, it is agreed that Eastern Telecommunications Philippines, Globe Telecom, Inc.[,] InfiniVAN, Inc. contracted FMCS to carry out the Services required by Eastern Telecommunications Philippines, Globe Telecom, Inc.[,] InfiniVAN, Inc. Further, FMCS is allowed to subcontract the scope of work in whole or in part to any third party or subcontractor.Assuming the subcontracted works pertain only to surveys or reports, and not the physical act of constructing the cable network, it still involves work that is crucial to the latter's accomplishment and completion. It is thus related to and connected with a construction project within the Philippines. I thus hesitate to find that there is no overarching construction contract governing in this case.
WHEREAS, in the Service[s] Agreement by and between Eastern Telecommunications Philippines, Globe Telecom, Inc.[,] InfiniVAN, Inc., and Fleet Marine Cable Solutions Inc. dated 7 December 2020, parties therein will build and construct a new high capacity domestic fiber-optic submarine network that will connect various islands in Luzon, Visayas and Mindanao at the highest quality possible but at the most cost-efficient means on an ownership basis.[18]
Arbitration, "[b]eing an inexpensive, speedy [,] and amicable method of settling disputes . . . is encouraged by the Supreme Court." If any doubt will arise, it "should be resolved in favor of arbitration."Given these circumstances, I find that the dispute between FMCS and MJAS fall within the jurisdiction of the Construction Industry Arbitration Commission.In LM Power Engineering Corp. v. Capitol Industrial Construction Groups, Inc., this Court explained the rationale behind this policy:
Aside from unclogging judicial dockets, arbitration also hastens the resolution of disputes, especially of the commercial kind. It is thus regarded as the "wave of the future" in international civil and commercial disputes. Brushing aside a contractual agreement calling for arbitration between the parties would be a step backward.
Consistent with the above-mentioned policy of encouraging alternative dispute resolution methods, courts should liberally construe arbitration clauses. Provided such clause is susceptible of an interpretation that covers the asserted dispute, an order to arbitrate should be granted. Any doubt should be resolved in favor of arbitration.[19] (Citations omitted)